Northern Aqueduct Phase 5
Description:
Permanent Lateral Support
Client:
Main Contractor:
Quantity Surveyor:
Location:
Year:
Scope of Work:
Ethekwini Municipality, Water & Sanitation Unit
Icon Construction
Resevoir Hills, Durban
2019
The project required a permanent lateral support system to stabilise approximately 675m2 of weathered rock face and fill material.
This was achieved by installing over 180 anchors, drilled to various depths in the rock, 90 gabion anchors and approx. 670m2 of welded mesh reinforced shotcrete and geocomposite band drains.
Northern Aqueduct Phase 5 - Proposed pipeline route
Photo taken 15/05/2019