top of page

Millchem
Description:
Client:
Main Contractor:
Project Engineer:
Quantity Surveyor:
Location:
Year:
Scope of Work:
Embankment stabilisation
Millchem Packaging
GBJ Developments
Martin And Associates
Randworth Close, Redhill
2025
The embankment stabilisation involved installing 600mm diameter CFA piles to form a contiguous piled wall midway down the embankment, with 13m long, 127mm diameter soil nails were installed through the concrete capping beam. GBJ Developments then backfilled behind the capping beam and reinstated the embankment using Terramesh.
bottom of page